21.07.2026
8 min read

Anyone procuring capacity from 2027 will be negotiating against the current EnEfG (Energy Efficiency Act) and a cabinet draft that could still shift thresholds and PUE (Power Usage Effectiveness) pathways. At the point of handover, the marketing brochure ends: waste heat, grid connection, and measured data decide before the contract is signed-not the glossy pages.

Key Takeaways

  • Effective: Commissioning from 1 July 2026. New data centres commissioned on or after this date must achieve a PUE of ≤ 1.2 and at least 10 % reused energy; for commissioning from 2027 and 2028 respectively, the planned energy shares rise to 15 % and 20 %. The PUE pathway must be met within two years of commissioning. The EnEfG itself has been in force since November 2023; 1 July 2026 is the deadline for the new-build PUE pathway.
  • Draft (Cabinet 24.06.2026) remains a draft. The government draft keeps the new-build PUE at ≤ 1.2 but extends the compliance period to four years, relaxes existing pathways, raises the application threshold to 500 kW installed IT load, and removes the obligation to install a heat-transfer station. Bundestag and Bundesrat will deliberate until autumn; the parliamentary process and the date of entry into force are open. Until then, the strict version applies.
  • Procurement hinges on evidence. Before signing, the scope, commissioning date, measured or planned PUE, waste-heat exemptions, and reporting obligations-each marked “effective” or “draft”-take precedence over any brochure promises.

RelatedDespite PUE Relaxation: Data Centres to Consume 21.3 bn kWh in 2025  /  When the Factory Floor and Data Centre Become One Network

The brochure ends at the transfer station

The same scene plays out at many sites across the DACH region. Behind the data centre lies the transfer station. Pipes, metering points and interfaces to the district heating network stand side by side. On the table in the adjoining meeting room are site sketches, load profiles and a presentation promising efficiency gains.

The procurement team wants hard numbers. When does the capacity go live? What PUE is set as the design target-and what is the measured operating value? Which loads feed into the meter when electricity is used to upgrade waste heat? The brochure is silent at precisely these points. That is where the contract logic begins.

At the transfer station today hangs the question of proof: who supplies heat, who measures it, who documents the exception in the PUE calculation. The cabinet draft dated 24 June 2026 proposes dropping the obligation to install a heat transfer station. The contract now being signed runs longer than the legislative process that Bundestag and Bundesrat will carry through to autumn or winter 2026.

Anyone claiming efficiency must present it before the signature-with date, measurement method and ownership.

The key date in the Energy Efficiency Act hinges on the commissioning date. Ground-breaking and contract signing do not shift the path assignment. Buying colocation, managed capacity, edge sites or hyperscaler regions also means buying the commissioning risk. The operator controls the schedule. The customer controls which assurances make it into the contract.

1 July 2026
In-force (commissioning key date): data centres commissioned on or after this date must reach a PUE of at most 1.2 within two years of commissioning. Existing sites commissioned before 1 July 2026 remain on the paths PUE ≤ 1.5 until 1.7.2027 and PUE ≤ 1.3 until 1.7.2030. Electricity used for waste-heat upgrading systems is excluded from the PUE calculation.
24 June 2026
Draft (Cabinet 24.06.2026), not yet law: government draft “Act to Accelerate Implementation of the Energy Efficiency Directive”. New build: PUE remains ≤ 1.2, to be achieved on a yearly average within four years of commissioning. Existing sites: from 1.7.2027 PUE ≤ 1.6, from 1.7.2030 PUE ≤ 1.4. The application threshold rises sharply-to 500 kW installed IT power. Heat transfer stations are no longer mandatory; internal waste-heat use is recognised; exceptions apply where economic feasibility is lacking, verified by cost-benefit analysis. Reporting obligations are substantially reduced to large plants with more than 1 MW nominal total energy input; the duty to provide information to heat-network operators is removed. Referred to the Bundestag; entry into force expected for autumn or winter 2026.

The tension sits exactly between these two levels. Today the stricter version applies. At the same time a cabinet draft is on the table that would relax thresholds, PUE deadlines, waste-heat obligations and reporting logic. Anyone negotiating capacity from 2027 onward is writing terms against a legal framework that can still shift. Every figure in the contract therefore needs a marker: in-force or draft (Cabinet 24.06.2026).

≤ 1.2
In-force: PUE ceiling for data centres commissioned on or after 1 July 2026, to be reached within two years of commissioning. Draft (Cabinet 24.06.2026): value remains ≤ 1.2, deadline extended to four years on a yearly average.
Source: EnEfG, in-force version (commissioning key date); government draft Cabinet 24.06.2026

Complementing this, the European Commission has announced a Data-Centre Energy-Efficiency Package for Q2 2026. The Energy Efficiency Directive introduces reporting obligations and sustainability metrics for data centres. National PUE pathways and European reporting lines therefore run in parallel. For procurement this means: evidence formats must not narrow down to a single metric.

What applies from commissioning on 1 July 2026

For the buyer of capacity, the allocation of the site comes first. If the space is commissioned before July 2026, the existing paths apply. If it is commissioned on or after 1 July 2026, the applicable new-build value of at most 1.2 applies within two years. The finer details lie in measurement thresholds, exceptions, and – once the draft becomes law – in whether the site still falls within the scope of application.

Power for systems that upgrade waste heat is excluded from the PUE calculation. This may sound technical, but contractually it is delicate. Anyone who specifies PUE in the SLA needs a clear definition of which loads are included in the meter and which remain outside. Otherwise, operations risk a calculation dispute instead of a control metric.

The government draft adopted by the cabinet on 24 June 2026 keeps the new-build PUE at ≤ 1.2 and extends the achievement period to an annual average of four years. For existing sites it proposes PUE ≤ 1.6 from 1 July 2027 and PUE ≤ 1.4 from 1 July 2030. For procurement, the raising of the application threshold to 500 kW installed IT power often carries more weight: many mid-sized data centres fall outside the scope. At the same time, heat transfer stations are no longer mandatory, internal use of waste heat is recognised, and an exception for cases lacking economic feasibility is added. Reporting obligations shrink to large plants with more than 1 MW nominal total energy input; the duty to provide information to heat-network operators is removed. All of this reflects the Marker draft (Cabinet 24.06.2026).

Here the operator’s logic becomes thin as soon as it only delivers planned PUE and marketing ERF. Procurement needs the ownership question: who supplies the measured value? Who is liable if the value is missed after commissioning? Who documents waste-heat exceptions and the measurement threshold for upgrade systems? Who verifies the scope against the current and the draft threshold? Without these roles, efficiency remains a presentation veneer.

Three risks regularly surface in ongoing tenders. First, the schedule slips past the cut-off date – and with it the applicable path. Second, the contract stores only a design value while operations measure a different one. Third, waste heat appears in the prospectus while heat off-takers, transfer arrangements and measurement concept are missing from the appendix – and the draft simultaneously puts the obligation for a transfer station up for debate. Each of these risks can be addressed before signature.

Which Documentation Must Be in Place Before Signing

The first step is a documentation checklist in the tender package-before the final price discussion. CIOs and procurement demand the same set of documents for colocation, managed capacity, and on-campus expansions. The list is kept deliberately concise. It separates current law from draft provisions (Cabinet 24.06.2026).

On the table must be: assessment of the scope of application: applicable from 300 kW non-redundant electrical rated connection capacity; in the draft from 500 kW installed IT power.; planned and binding commissioning date; classification as existing or new-build path; PUE target value with marker current or draft; measurement concept including exception for power used to upgrade waste heat; handling of heat transfer and internal waste heat utilisation; role matrix for reporting and escalation chains; as well as contract mechanisms for rectification if the operational value misses the guaranteed range.

If you operate your own campus capacity, you apply the same set internally. Facilities, IT, and procurement clarify who measures the PUE and who releases waste heat interfaces. Even today, clear data handover eases data-centre operations and internal audit trails. Once the draft becomes law, the scope of application and the streamlined reporting logic for large facilities move further into focus.

Site criteria gain weight in the process. Grid connection, nearby heat off-takers, and realistic utilisation-path planning determine whether a PUE target can be sustained in operation. A site without off-takers makes waste-heat narratives fragile. A site with off-takers but no measurement concept makes them unprovable. Both gaps surface in the next review-regardless of whether the transfer station remains mandatory under the future law.

Contractually, it pays to separate assurances from outlooks. Current PUE paths can be framed as hard operational metrics. Draft figures belong in a change mechanism with a review date-as soon as the cabinet draft becomes enforceable law. This keeps the contract actionable without treating the draft as binding regulation.

The concrete first step next week: compile existing and planned capacity contracts with commissioning from 2026 in a single overview. For each site, enter commissioning date, path classification, scope assessment, and available PUE evidence. Feed any gaps back to the operator. Only then follow renegotiation or a new tender.

Efficiency without evidence is an operational risk in the EnEfG context. With date, measurement method, and ownership, it becomes a controllable contract variable. That is where the next data-centre contract will stand or fall on 1 July-and against the cabinet draft.

Frequently Asked Questions

Which reference date determines the PUE path?

The decisive factor is the date the data center becomes operational. Start of construction and contract signing do not alter the path. For buyers, the binding go-live schedule in the contract is therefore the key date.

What applies to data centers commissioned on or after 1 July 2026?

Data centers commissioned on or after 1 July 2026 must achieve a PUE of no more than 1.2 within two years of going live. Existing facilities commissioned earlier remain subject to the paths PUE ≤ 1.5 until 1 July 2027 and PUE ≤ 1.3 until 1 July 2030 (current rules). 1 July 2026 is the reference date for the new-build path. The EnEfG itself has been in force since November 2023.

What changes does the cabinet draft of 24 June 2026 introduce?

Draft (Cabinet 24.06.2026): new-build remains at PUE ≤ 1.2, to be achieved as a yearly average within four years; existing facilities PUE ≤ 1.6 from 1 July 2027 and PUE ≤ 1.4 from 1 July 2030; application threshold 500 kW installed IT load; obligation to install a heat transfer station removed; reporting obligations limited to large installations above 1 MW. All of this is still draft and may change during the parliamentary process. Until entry into force, the stricter version applies.

How is waste heat factored into the PUE calculation?

Current rules continue to exclude electricity used by systems that upgrade waste heat from the PUE calculation (§ 11 para. 2 EnEfG). Contracts therefore need a clear metering boundary and documentation of excluded loads. Draft (Cabinet 24.06.2026): heat transfer stations no longer mandatory; internal use and an exception for cases where economic feasibility is lacking are added.

What evidence should procurement request before signing?

Scope (including draft: 500 kW installed IT load), commissioning date, path assignment, PUE marked as current or draft, metering concept including exception for electricity used to upgrade waste heat, roles for reporting and a mechanism for when operational values are missed. Without these points, efficiency remains an intention.

Image source: AI-generated (Mai 2026)

Share this article:

Also available in

More Articles

04.08.2026

Local AI: Governance Before Hardware Purchase

Benedikt Langer

10 min readFour developments over two weeks show that locally operated AI goes far beyond the tech stack. ...

Read Article
03.08.2026

AI Regulation: Up to 3 Percent of Corporate Revenue

Tobias Massow

5 min read Article 50 of the AI Act has bound providers and deployers to concrete transparency obligations ...

Read Article
31.07.2026

You are paying for the R&D of the next competitor

Benedikt Langer

4 min read You are funding the R&D of your next competitor and calling it AI transformation. Frontier ...

Read Article
29.07.2026

Model Harness Instead of Model Marriage: Who Controls the AI Chain?

Eva Mickler

6 min read The lock-in is shifting from the individual model to the orchestration layer. Those who don’t ...

Read Article
28.07.2026

Washington decides which AI is allowed to run here

Eva Mickler

6 Min. read time In just eight days, Washington has shifted the dispute over Chinese AI models from ...

Read Article
23.07.2026

Orphaned Access: The Silent Cybersecurity Gap

Benedikt Langer

5 Min. Read Time Service accounts, API keys, and AI agents often outnumber human accounts. Many of these ...

Read Article
A magazine by Evernine Media GmbH